Hi expert,
I have a "normal change" with the state "in developement".
I add to change document an external transport request. Everything ok, but in the managed system the new TR is ready for import into test system and the normal change is still "in developement".
The expected behavior is that this happens after you set the action "pass normal change to test."
This failure creates many problems because we have a scheduled JOB that import the TR into test system.
Could you please help me?
Thanks in advance
Silvio
More info:
Solution Manager 7.1 SP13