Hello,

 

In your first post you said:

1. If the check date of the production version is earlier (say 30.11.2015) than the valid from date of BOM (say 01.01.2016), then will the production version go for inconsistency.

 

2. We have a few production versions for which the Check date is earlier than the BOM “Valid
from” date, but the status is green. Can you please let us know the cause.

 

1. The first point is correct. IF the valid from date of your PV is 30.11.2015, but the valid from date is 01.01.2016, then you should see an error when you check the PV.


2. If the valid from date of your PV is earlier than the valid from date of the BOM I would think that someone change the valid from date of the BOM. It is not possible to have that situation. If you check the PV now that the valid from date of your PV is earlier than the valid from date of your BOM you will get an error.


Note that any of your screenshots describe the situation mentioned in point 2.

 

Kind Regards,

MAriano